Overall Progress Status

On track 77%
Delayed 11%
At Risk 11%

1.Contractor has mobilised to site

2.Topographical survey and geotechnical investigations ongoing.

3.Fencing materials have been procured and fencing works have commenced.

4.Site office portacabins have been deployed to site, security personnel for site security purposes have also been deployed.

See below photos from progress report

1.Contractor has mobilised to site.

2.Site clearing activities and civil works ongoing.

3.Topographical survey and geographical investigations have been conducted and the report has been submitted to the REA for formal approval

4.Fencing commenced and near completion.

5.Final vendors for major equipment have beenĀ  identified by the Contractor and a Purchase Order has been issued for the battery equipment and Exeron system.

6. Site office portacabins have been deployed to site, security personnel for site security purposes have also been deployed

1.Contractor has mobilised to site

2.Topographical survey and geotechnical investigations are in progress.

3.Fencing materials have been procured and fencing works have commenced.

4. Site office portacabins have been deployed to site, security personnel for site security purposes have also been deployed.

1.Contractor has mobilised to site.

2.Site clearing and civil works activities ongoing

3.Surveys and Soil investigations have been conducted and the report has been submitted and approved by REA.

4.Fencing works is ongoing

1.Contractor has mobilised to site

2.Topographical survey and geotechnical investigations have been completed.

3.Project Site Office deployed to Site

4.Fencing activities are ongoing.

1.Contractor has mobilised to site.

2.Site clearing activities and civil works ongoing

3.Topographical survey and geotechnical investigations have been conducted and the report has been submitted to the REA for formal approval

4.Fencing activities are ongoing.

1.Contractor has mobilised to site

2.Site office caravan has been positioned on site

3.Site clearing activities have been completed

4.Topographical survey has been completed

5.Cable relocation has been completed

6.Soil investigation is ongoing and nearing completion

7. 25% of the detailed design drawings have been approved for the contractor to commence work

1.Contractor has mobilised to site.

2.Site clearing activities and civil works ongoing

3.Topographical survey and geotechnical investigations have been conducted and the report has been submitted to the REA for formal approval

4.Fencing has commenced

5.Final vendors for major equipment have been determined by the Contractor and a Purchase Order has been sent for the some of the equipment such as the batteries and the inverter system.

1.Contractor has mobilised to site

2.Site office caravan has been positioned on site

3.Site clearing activities have been concluded

4.Site convenience construction has been completed

5.Topographical survey has been completed

6. Geotechnical investigation has been completed.