The university projects under the EEP have been developed sustainably in Phases.

EEP Phase 1 Universities are shown below:

ABUBAKAR TAFAWA BALEWA UNIVERSITY TEACHING HOSPITAL, BAUCHI.

REGION: NORTH EAST

Image module

Abubakar Tafawa Balewa (ATBU) University was founded in 1980. The Gubi campus is powered by the Energizing Education Programme. The University occupies 170 hectares of land. The total population of the University for undergraduate and post graduate students, academic and non-academic staff as at July 2016 was 18,284.

TECHNICAL BREAKDOWN
Lot Technology Contractor
9 Solar Hybrid Sterling & Wilson Nigeria Limited

 

BIWEEKLY PROGRESS REPORT ENDING 2ND JUNE

1. Site clearing and fencing has been completed.

2. Topographical survey and geotechnical investigation reports have been submitted and approved by REA.

3. Site office portacabins have been deployed to site, security personnel for site security purposes have also been deployed.

4. FATs for all major equipment has been conducted.

5. All equipment related civil works have been completed.

6. WTC building is near completion.

7. Installation of PV panels, Power conditioning system, batteries and other materials have been completed.

8. Commissioning tests have been completed with NEMSA invited to participate in witnessing the tests.

9. Street lighting is 100% completed.

10. Plant test running for 24 hours daily is currently ongoing, while official commissioning is still pending.

 

BIWEEKLY PROGRESS GALLERY WEEK ENDING 2ND JUNE

BAYERO UNIVERSITY, KANO.

REGION: NORTH WEST

Image module

Bayero University Kano was founded in 1975 its bodies are the University Council and the Senate. The university was initially named Bayero University College before being upgraded to Bayero University. As at July 2016, the total population of the University including undergraduate and post-graduate students, academic and non-academic staff was 31,462
Bayero University is located in Kano, The main campus is powered by the Energizing Education Programme. It is situated on a 1,369 hectares located along the Gwarzo Road, Kano

TECHNICAL BREAKDOWN
Lot Technology Contractor
7 Solar Hybrid Metka West Africa Limited

 

BIWEEKLY PROGRESS REPORT WEEK ENDING 2ND JUNE

1. Topographical survey and geographical investigations have been conducted and the report has been submitted and approved by REA.

2. FATs for all major equipment has been conducted.

3. Internal Road and site Access Roads have been completed.

4. All plant equipment & street-lighting have been fully installed and commissioned.

5. All major equipment has been installed and the MV distribution works from Plant to connection has been completed & commissioned.

6. Workshop & Training Center has been completed.

7. The BUK site was commissioned by the Vice President; Prof. Yemi Osinbajo on 3rd September 2019, went through a test-running phase and has been providing power to the university.

 

BIWEEKLY PROGRESS GALLERY WEEK ENDING 2ND JUNE

 

MEDIA FOOTAGE

UNIVERSITY OF AGRICULTURE, MAKURDI, BENUE STATE

REGION: NORTH CENTRAL

Image module

The University of Agriculture, Makurdi was founded in January 1988 and its bodies are the University Council and the Senate. The University of Agriculture, Makurdi is situated on 8,000 hectares. It is located on the Makurdi – Lafia road in Makurdi, the capital of Benue State, in North-Central Nigeria, about 300 Kilometers to the southeast of Abuja, Nigeria’s Federal Capital.

The Campus is located north of the River Benue, near the township of Makurdi North. As at July 2016, the combined population of students and staff was 17,  864.

TECHNICAL BREAKDOWN
Lot Technology Contractor
8 Solar Hybrid Sterling & Wilson Nigeria Limited

 

BIWEEKLY PROGRESS REPORT WEEK ENDING 2ND JUNE

1. Site clearing, grading and fencing have been completed.

2. Topographical survey and geotechnical investigations reports have been submitted and approved by REA.

3. Site office portacabins have been deployed to site, security personnel for site security purposes have also been deployed.

4. Project site borehole works have been completed.

5. FATs for all major equipment has been conducted.

6. All plant equipment required for project completion have been delivered to site.

7. WTC building is currently under construction and is 58% completed.

8. Streetlight installation activities are currently ongoing.

9. Internal and Access Road works are ongoing.

10. MCR and the Battery Bank buildings are completed with all panels and batteries installed.

11. The PV installation has been completed and alignment is ongoing.

 

BIWEEKLY PROGRESS GALLERY WEEK ENDING 2ND JUNE

FEDERAL UNIVERSITY OF PETROLEUM RESOURCES EFFURUN, DELTA STATE

REGION: SOUTH SOUTH

Image module

The Federal University of Petroleum Resources Effurun was founded in 2007. Its governing bodies are the Council and the Senate. In January 2006, the Federal Government approved the takeoff of the college of petroleum and gas engineering of the University of Benin at Effurun, near Warri in Delta Sate. It was later upgraded to a full-fledged university in the year 2007.

The University is located at Ugbomro, Uvwie Local Government Area, along warri-Port Harcourt Road, before Agbarho Bridge. The University Campus covers 163,151 hectares of land. The campus is not as swampy as the other parts of Warri areas. As at July 2016, the population of the University for undergraduate and staff totalled 4,000

TECHNICAL BREAKDOWN
Lot Technology Contractor
5 Solar Hybrid Metka West Africa Limited

 

BIWEEKLY PROGRESS REPORT WEEK ENDING 2ND JUNE

1.Surveys and soil investigations have been conducted and the report has been submitted and approved by REA.

2. Fencing works as well as equipment foundation works have been completed.

3. Civil works for Internal Road has been completed.

4. Factory Acceptance Tests for all major equipment has been concluded.

5. 5Nos Battery Containers and Diesel Generating sets have arrived the site, been installed and commissioned. Distribution network Cables have been laid and terminated on the Ring Main Unit (RMU).

6. PV Panels and all other equipment have been installed and completed.

7. Pre-commissioning tests have been conducted with the plant ready for test operation.

8. Workshop and Training Centre has been completed with all training equipment delivered to site.

 

BIWEEKLY PROGRESS GALLERY WEEK ENDING 2ND JUNE

FEDERAL UNIVERSITY NDUFU – ALIKE, IKWO, EBONYI STATE

REGION: SOUTH EAST

Image module

Federal University Ndufu-Alike Ikwo is a modern University established in 2011 and is located in the serene agricultural environment of Ikwo in Ebonyi State, South East Geopolitical zone of Nigeria. Fondly called FUNAI, the University prides itself as the home of soaring eagles, after its totem bird, the eagle, whose soaring image is prominent on the University logo. In 2011 the University initially took over the facilities of Government girls college Ndufu – Alike. After the take over, the University acquired additional land space to create the permanent site in its present form.

The main campus of The Federal University, Ndufu-Alike Ikwo (FUNAI) is situated on 435.72 hectares and is located along the major road to Ikwo. The University began operations with only a takeoff site but soon expanded to a permanent site. The permanent site is an extension of the takeoff site with the two campuses within the same location being powered by the Energizing Education Programme.

The University administrative staff are currently operating from the permanent site and the female students are currently living in the hostels situated at the permanent site. As at July 2016, the combined population of both students and staff on campus was 3,590

TECHNICAL BREAKDOWN
Lot Technology Contractor
4 Solar Hybrid Sterling & Wilson Nigeria Limited

 

BIWEEKLY PROGRESS REPORT WEEK ENDING 2ND JUNE

1. Streetlight installations have been completed.

2. Civil works for Internal Roads has been completed.

3. Main Gatehouse (MGH) as well as Septic Tank for MGH has been completed.

4. PV Panel installation has been completed.

5. WTC has been completed

6. Site Pre-Commissioning Tests was conducted prior to commissioning of the project site.

7. Site was commissioned by the Vice-President; Prof. Yemi Osinbajo on 2nd August 2019.

8. Plant operations have been ongoing and has attained over 243 days of 24 hours power supply.

 

BIWEEKLY PROGRESS GALLERY WEEK ENDING 2ND JUNE

 

MEDIA FOOTAGE

NNAMDI AZIKIWE UNIVERSITY, AWKA, ANAMBRA STATE

REGION: SOUTH EAST

Image module

The Nnamdi Azikiwe University was founded in 1992 and t’s governing bodies are the University Council and the Senate. The University took over the former Anambra State University of Technology (ASUTECH), and ollowing the split of the former Anambra State into Anambra and Enugu States in 1991, the former Awka and Nnewi campuses of ASUTECH became Nnamdi Azikiwe University. The Awka campus is being powered by the Energizing Education Programme.

The University was taken over by the Federal Government as the first non-residential University in the country with effect from September 1, 1992. The main campus of Nnamdi Azikiwe University is situated on 502 hectares, with coordinates 6°14’40.4″N 7°07’16.9″E, and is located along the Enugu to Onitsha express way. It lies within Awka, the capital of Anambra State.

TECHNICAL BREAKDOWN
Lot Technology Contractor
3 Solar Hybrid Metka West Africa Limited

 

BIWEEKLY PROGRESS REPORT WEEK ENDING 2ND JUNE

1. Site clearing activities, levelling and fencing have been completed.

2. Site office and project signboard have been mounted on site.

3. Topographical survey and geotechnical investigation report have been submitted and approved by REA.

4. Equipment foundations have been completed.

5. FATs for all major equipment have been conducted.

6. Ongoing site drainage works.

7. MV distribution and LV cable works have been completed and Power Transformers have been installed.

8. Major equipment has been installed on site, while Workshop and Training Centre works is ongoing.

9. PV Panel, DG, Battery Installation have all been completed.

10. Ongoing Streetlight termination works.

11. Installation of water distribution system on site for PV cleaning is nearly completed

 

BIWEEKLY PROGRESS GALLERY WEEK ENDING 2ND JUNE

OBAFEMI AWOLOWO UNIVERSITY AND TEACHING HOSPITAL, ILE-IFE, OSUN STATE

REGION: SOUTH WEST

Image module

Obafemi Awolowo University (OAU) is a Federal Government owned and operated University. The University was founded in 1961 and classes commenced in October 1962 as the University of Ife. It was renamed Obafemi Awolowo University on 12 May 1987 in honor of Chief Obafemi Awolowo, first premier of the Western Region of Nigeria. OAU Occupies 2,020 hectares (5000 acres) of land in an urban town called Ile-ife, Osun State, Nigeria. As at October 2016, the population of the University for undergraduate, postgraduate and members of staff was 37,345.

The Obafemi Awolowo University Teaching Hospital Complex is one of the first generation of Teaching hospitals established by the Federal Government in 1967, when the defunct Western State Government of Nigeria resolved to establish a medical School in its State university at Ile-Ife.

The university and its teaching hospital are being powered by the Energizing Education Programme.

TECHNICAL BREAKDOWN
Lot Technology Contractor
1 Gas-Fired Power Plant Sterling & Wilson Nigeria Limited

 

BIWEEKLY PROGRESS REPORT WEEK ENDING 2ND JUNE

1. Site office has been positioned on site.

2. Site clearing, levelling activities and fencing have been completed.

3. Geotechnical investigation has been submitted and approved by REA.

4. Civil works for engine foundations have been completed and foundation for the Retaining Walls have been casted.

5. Diesel Generator (DG) Set foundation has been casted.

6. Rehabilitation of Streetlight works and retrofitting of bulk heads is 70% completed.

7. Factory Acceptance Tests (FATs) for all major equipment and LNG infrastructure has been conducted.

8. Site drainage works have commenced as well as casting and planting of precast Streetlight plinths.

9. PV Plant access road works have been completed.

10. Works on Panel Room and other BOP Foundation is ongoing.

11. Workshop & Training centre foundation has been completed.

12. Liquefied Natural Gas (LNG) Civil works are about to commence.

13. Processing of DPR permit for plant Liquefied Natural Gas is ongoing.

14. All Gas Engines and Plant machineries and balance of Plant items are offshore, ready for shipment.

15. All LNG infrastructure are in Nigeria, ready to be transported to the site.

 

BIWEEKLY PROGRESS GALLERY WEEK ENDING 2ND JUNE

UNIVERSITY OF LAGOS, LAGOS STATE

REGION: SOUTH WEST

Image module

The University of Lagos – popularly known as UNILAG – is a Federal Government research university in Lagos State, southwestern Nigeria. The Eric Ashby Commission on Post School Certificate and Higher Education was established by the Nigerian Government in May 1959.

Following the acceptance of the UNESCO Commission’s report, the University of Lagos was established on 22 October 1962 on the authority of the University of Lagos Act of 1962.

University of Lagos is located in the mainland of Lagos. It is largely surrounded by the scenic view of the Lagos lagoon on 802 acres of land in Akoka, North Eastern part of Yaba, Lagos. As at July 2016, the population of the University undergraduates, postgraduates and members of staff was 59,371.

TECHNICAL BREAKDOWN
Lot Technology Contractor
2 Gas-Fired Power Plant Sterling & Wilson Nigeria Limited

 

BIWEEKLY PROGRESS REPORT WEEK ENDING 2ND JUNE

1.Site clearing activities have been completed.

2. Cable relocation has been completed.

3. Soil investigation has been completed and report submitted to REA for approval.

4. Site reclamation works for the first phase of sand-filling has been completed.

5. Site Fencing has been completed.

6. Installation of Streetlights and retrofitting of bulk heads has been completed.

7. Factory Acceptance Tests for all major equipment have been conducted.

8. All Gas Engines and Plant machineries and balance of Plant items are offshore, ready for shipment.

9. All LNG infrastructure are in the country, ready to be transported to site.

 

BIWEEKLY PROGRESS GALLERY WEEK ENDING 2ND JUNE

USMANU DANFODIYO UNIVERSITY, SOKOTO STATE

REGION: NORTH WEST

Image module

Usmanu Danfodiyo University was founded in September 1975. The University currently has a Solar Installation that powers the UDUNET and the main campus library with a combined capacity of 15kW, 10kW powering the UDUNET and 5kW powering the Library.

The Usmanu Danfodiyo University main campus is being powered by the Energizing Education Programme.

TECHNICAL BREAKDOWN
Lot Technology Contractor
6 Solar Hybrid Metka West Africa Limited

 

BIWEEKLY PROGRESS REPORT WEEK ENDING 2ND JUNE

1. Site clearing and fencing has been completed.

2. Topographical survey and geotechnical investigation reports have been submitted and approved by REA.

3. Civil works for Internal Roads is ongoing alongside Equipment Foundations.

4. FATs for all major equipment has been conducted.

5. MV distribution network cables have been laid up to the interconnection point and the RMU installed at the same point.

6. Foundation works for the Workshop & Training Centres is at an advance stage of construction.

7. Streetlight works is almost completed.

8. PV Panels and inverter installation has been completed.

 

BIWEEKLY PROGRESS GALLERY WEEK ENDING 2ND JUNE
CURRENT STATUS
 

FOCUS ITEMS FOR NEXT REPORTING PERIOD

TECHNICAL    

– Preliminary and detailed design drawings are undergoing reviews while over 90% have been approved.

– Civil construction has been completed in all Solar sites while civil works have commenced at the gas sites.

– Fencing works have been completed across all the 9 project sites.

– Equipment foundation works have reached completion in 8 out of 9 sites

– FATs on major equipment have been conducted for all the project sites.

– Access and Internal Roads and Site Drainages have been completed at most of the Solar sites, while same is ongoing for some other sites.

– All major equipment has been installed at all the Solar sites, while major equipment for the Gas sites have been purchased and ready for shipment/delivery to the project sites, however this will be carried out upon the required payment that is due to the contractors for these sites.

– Installation of Streetlights have commenced across all sites and have been completed across 5 project sites.

– The FUNAI and BUK project sites were commissioned on 2nd August and 3rd September 2019 respectively, while ATBU and FUPRE are the next project sites to be commissioned.

– Workshop/training Center for FUAM, NAU and UDUS are in progress, while UNILAG and OAU are at various stages of construction. The WTC materials for the Gas sites are however on site and construction of the WTC will commence as soon as practicable, considering the COVID-19 situation.

– In addition to the commissioned sites, PV Panel installation has also been completed across all the solar sites.

– Pre-commissioning Tests have been completed at FUPRE, ATBU and FUAM

 

 

– Continue ongoing review and approval of the detailed design drawings.

– Continue ongoing civil construction works on gas sites.

– Hold Progress Meetings with Contractors.

– Continue ongoing streetlights installations and construction of the Workshop and Training Centers.

– Complete PV Panel alignment at the FUAM site.

-Develop Sustainability Plan Governance Structure/Model

 

 

FINANCIAL
   

– All project sites have received complete mobilization payment from the Sovereign Green Bond Fund and FGN.

– Except for UNILAG which is yet to receive 3rd payment, all other project sites have received full 2nd and 3rd payment from the Sovereign Green Bond Fund & FGN.

– In addition, ATBU and OAU sites have received up to 4th payment, FUAM has received up to 6th payment, while FUNAI and BUK have received complete payment.

– Invoices for further payments have been received for some sites, however this has not been paid due to unavailability of funds.

 

 

 

Payment on all outstanding milestone invoices.

– Funding from Development partners and donor organizations, in order to fund the EEP Phase I Project Management Team.

– Renewal of contracts for members of the Review Team and Site/Resident Engineers

– Source for special intervention funds to pay the EPC Contractors for additional costs incurred on the EEP Phase 1 projects.

 

LEGAL & REGULATORY    

– MOUs were signed between REA and the Phase 1 Universities.

– Certificates of No Objection to Award Contracts were granted by the BPP.

– FEC approval for same was granted.

– Captive Permits were issued by NERC for all 9 Phase 1 projects.

– Land surveys for all project sites were certified by the surveyor general.

– Received approved EIA’s for all sites from the Fed. Min. of Environment.

– Executed EPC Contracts with METKA West Africa and Sterling & Wilson Nigeria Ltd.

– First draft of the Sustainability Plan agreement has been developed

 

 

– Finalize O & M Agreement

– Ensure compliance with the EPC Contracts.

– Develop Sustainability Plan Agreement

PROJECT DOCUMENTS REVIEW AND APPROVALS REPORTS
S/N EPCC DOCUMENTS SUBMITTED TO DATE DATE IN DATE OUT DEADLINE STATUS REMARKS
1 METKA NG UNIVERSITIES – DOCUMENT SUBMISSION V-0039 – CONTROL SYSTEM WIRING DIAGRAMS, DATASHEETS AND MANUALS – BUK (Α-450) 8/2/19 25/2/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
2 NG UNIVERSITIES – DOCUMENT SUBMISSION D-0051 – CABLES ROUTING LAYOUT DRAWING AND CABLE DITCHES TYPICAL SECTIONS (Α-572) 20/02/19 26/02/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
3 NG UNIVERSITIES – DOCUMENT SUBMISSION D-0056 – DRAINAGE LAYOUT & REPORT (Α-609) 22/02/19 27/02/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
4 NG UNIVERSITIES – DOCUMENT SUBMISSION D-0050 – SITE WATER DISTRIBUTION LAYOUTS (Α-571) 20/02/19 08/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
5 NG UNIVERSITIES – DOCUMENT SUBMISSION D-0053 – GA & LAYOUT DRAWINGS (Α-574) 20/02/19 05/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
6 NG UNIVERSITIES – DOCUMENT SUBMISSION D-0054 – CABLE LISTS (Α-575) 20/02/19 05/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
7 NG UNIVERSITIES – DOCUMENT SUBMISSION V-0037 – TRANSFORMERS FAT REPORTS – FUPRE (Α-203) 04/09/19 07/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
8 NG UNIVERSITIES – DOCUMENT SUBMISSION D-0015 – EXCAVATION REPORTS & LAYOUT DRAWINGS (Α-3623) 21/01/19 05/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
   9 STERLING & WILSON RE: 321, 322 (MDR 22) REA/EEP/ATBU/FUAM/FUNAI: EARTHING PIT CALCULATIONS DOCUMENTS SUBMISSION. 21/02/19 25/02/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
   10 118 (MDR 136) REA/EEP/UNILAG: UNIVERSITY CAMPUS STREET LIGHTING POLES DETAILS DRAWINGS SUBMISSION. 25/02/19 26/02/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
  11 369, 370 (MDR 257,264) REA/EEP/FUNAI: FOUNDATION AND COLUMNS DETAILS AND ROOF BEAMS LAYOUT- PLAN AND SECTIONS DRAWINGS SUBMISSION. 26/02/19 01/03/19   REVIEWED EPCC to revise in line with comments  and re-submit for further review and approval
  12 377, 378 (MDR 257,264) REA/EEP/FUAM: FOUNDATION AND COLUMNS DETAILS AND ROOF BEAMS LAYOUT- PLAN AND SECTIONS DRAWINGS SUBMISSION. 27/02/19 01/03/19   REVIEWED EPCC to revise in line with comments  and re-submit for further review and approval
  13 361, 362 (MDR 257,264) REA/EEP/ATBU: FOUNDATION AND COLUMNS DETAILS AND ROOF BEAMS LAYOUT- PLAN AND SECTIONS DRAWINGS SUBMISSION. 26/02/19 01/03/19   REVIEWED EPCC to revise in line with comments  and re-submit for further review and approval
  14 379 (MDR 42) REA/EEP/FUAM: MCR TRENCH LAYOUT DRAWING SUBMISSION. 26/02/19 02/03/19   REVIEWED EPCC requested to incorporate comments from the FUNAI submission, effect the requested revisions and resubmit.
  15 375, 376 (MDR 172,173) REA/EEP/FUAM: GROUND AND FIRST FLOORS PLANS-AIR CONDITIONING SERVICE LAYOUT DRAWINGS SUBMISSION. 26/02/19 02/03/19   REVIEWED EPCC mandated to provide floor dimensions of all rooms and partitions to enable conclusion.
  16 RE: 21, 76, 95 (MDR 6,7 AND 32) REA/EEP/ATBU/FUAM/FUNAI: PV SYST DOCUMENTS SUBMISSION. 20/02/19 02/03/19   PROVISIONAL APPROVAL granted EPCC to revise the submission based on the errors identified.
   17 359, 360 (MDR 172,173) REA/EEP/ATBU: GROUND AND FIRST FLOORS PLANS-AIR CONDITIONING SERVICE LAYOUT DRAWINGS SUBMISSION. 26/02/19 02/03/19   REVIEWED EPCC mandated to provide floor dimensions of all rooms and partitions to enable conclusion.
  18

STERLING & WILSON

 

 

 

 

367, 368 (MDR 172,173) REA/EEP/FUNAI: GROUND AND FIRST FLOORS PLANS-AIR CONDITIONING SERVICE LAYOUT DRAWINGS SUBMISSION. 26/02/19 02/03/19   REVIEWED EPCC mandated to provide floor dimensions of all rooms and partitions to enable conclusion.
  19 332, 333 (MDR 23) REA/EEP/ATBU/FUAM: LIGHTNING PROTECTION DESIGN CALCULATION DOCUMENTS SUBMISSION. 14/02/19 02/03/19   PROVISIONAL APPROVAL granted EPCC to revise in line with comments  and re-submit for further review and approval
  20 RE: 20 (MDR 32) RE: REA/EEP/ATBU: ARRAY AND PLANT LAYOUT SUBMISSION. 25/02/19 05/03/19   REVIEWED EPCC requested to revise the ATBU Array and Plant Layout drawing and re-submit for final approval.
  21 354 (MDR 285) REA/EEP/ATBU: DG FOUNDATION DESIGN CALCULATION DOCUMENT SUBMISSSION. 26/02/19 05/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
  22 381 (MDR 287) REA/EEP/FUNAI: BBR FOUNDATION DESIGN CALCULATION DOCUMENT SUBMISSION. 28/02/19 05/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
  23 RE: 202-205 (MDR 286, 290) REA/EEP/ATBU/FUNAI: MCR DESIGN AND FOUNDATION DESIGN CALCULATION SUBMISSION.

25/02/19

28/02/19

05/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
  24 RE: 73, 245 (MDR 32, 39) REA/EEP/FUAM: ARRAY AND PLANT LAYOUT AND STREET LIGHT LAYOUT DRAWINGS SUBMISSION. 22/02/19 06/03/19   PROVISIONAL APPROVAL granted EPCC to revise the Array and Plant layout and re-submit for final approval.
   25 RE: 143, 144, 145 (MDR 41) REA/EEP/ATBU/FUAM/FUNAI: MAIN CONTROL ROOM (MCR) ELECTRICAL EQUIPMENT LAYOUT FOR SOLAR PROJECTS SUBMISSION. 20/02/19 06/03/19   PROVISIONAL APPROVAL granted EPCC to revise in line with comments  and re-submit for further review and approval
   26 383 (MDR 318) REA/EEP/FUNAI: TRANSFORMER (DISTRIBUTION TRANSFORMER FOUNDATION DRAWINGS_300KVA & 500KVA) SUBMISSION. 04/03/19 06/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
  27

STERLING & WILSON

 

 

 

384, 385 (MDR 324) REA/EEP/ATBU/FUAM: WEATHER MONITORING SYSTEM DOCUMENTS SUBMISSION. 06/03/19 06/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
  28 386, 387 (MDR 308) REA/EEP/ATBU/FUAM: PV CONNECTORS DRAWINGS SUBMISSION. 06/03/19 06/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
  29 338 (MDR 5) REA/EEP/ATBU: WATER TEST REPORT DOCUMENT SUBMISSION. 20/02/19 07/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
  30 392 (MDR 285) FUAM: DG FOUNDATION DESIGN CALCULTION DRAWINGS SUBMISSION. 06/03/19 07/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
  31 388 (MDR 310) REA/EEP/ATBU: HT PANEL DOCUMENT/DRAWING SUBMISSION. 06/03/19 07/03/19   REVIEWED. EPCC to revise the ATBU HT Panel document/drawing and re-submit for approval.
RE: 340 (MDR 290) REA/EEP/FUAM: MCR DESIGN DRAWINGS SUBMISSION. 05/03/19 07/03/19   APPROVAL granted EPCC to submit stamped, signed and sealed hard-copies for documentation.
  32
  33 348, 349 (MDR 43, 45) REA/EEP/ATBU: MCR ILLUMINATION, AND ELECTRICAL AND POWER LAYOUTS DRAWINGS SUBMISSION. 22/02/19 08/03/19   APPROVAL granted EPCC to submit stamped, signed and sealed hard-copies for documentation.
    34   389, 390, 391 (MDR 184) REA/EEP/ATBU/FUAM/FUNAI: PERIMETER LIGHTING CABLE CALCULATION DOCUMENTS SUBMISSION. 08/03/19 08/03/19   REVIEWED EPCC given specifications and comments for revision.
  35

STERLING & WILSON

 

 

279 (MDR 254) REA/EEP/FUAM: DRAINAGE DETAILS-PLAN AND SECTIONS DRAWINGS SUBMISSION. 06/03/19 08/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
  36 350, 351 (MDR 43, 45) REA/EEP/FUAM: MCR ILLUMINATION, AND ELECTRICAL AND POWER LAYOUTS DRAWINGS SUBMISSION. 22/02/19 09/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
  37 373, 374 (MDR 169,170) REA/EEP/FUAM: GROUND AND FIRST FLOORS PLANS-SOIL AND WASTE WATER DRAINAGE LAYOUT DRAWINGS SUBMISSION. 26/02/19 10/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
  38 365, 366 (MDR 169,170) REA/EEP/FUNAI: GROUND AND FIRST FLOORS PLANS-SOIL AND WASTE WATER DRAINAGE LAYOUT DRAWINGS SUBMISSION. 26/02/19 10/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.
  39 357, 358 (MDR 169,170) REA/EEP/ATBU: GROUND AND FIRST FLOORS PLANS-SOIL AND WASTE WATER DRAINAGE LAYOUT DRAWINGS SUBMISSION. 26/02/19 10/03/19   APPROVAL granted. EPCC to submit stamped, signed and sealed hard-copies for documentation.